[BLDG-SIM] How to simulate VAV systems without cooling coils in eQuest
You can schedule the coil to be off via the
availability schedule.
Peter
Peter Alspach, P.E.
Associate
Arup
403 Columbia St., Suite 220
Seattle, WA 98104
T: 206-493-2226
C: 206-816-4902
F:
206-749-0665
E:
peter.alspach@xxxxxxxx
All,
In the northwest USA we often use
VAV systems without cooling for schools -- 100% outside air economizer
cooling, and 'off' for three months in the summer. The particular system I
want to model in eQuest is the standard VAV with heat recovery,
but I can't figure how to either define it without a cooling coil, or render the
cooling coil and chiller ineffective.
What is the best way to do
this?
Thanks
Brandon Nichols,
PE
Mechanical
HARGIS ENGINEERS
600 Stewart Street
Suite 1000
Seattle, WA 98101
www.hargis.biz
d
|
206.436.0400 c | 206.228.8707
o
|
206.448.3376 f |
206.448.4450
==================
You received this e-mail because you are subscribed
to the BLDG-SIM@xxxxxxxx mailing list. To unsubscribe
from this mailing list send a blank message to
BLDG-SIM-UNSUBSCRIBE@xxxxxxxx
____________________________________________________________
Electronic mail messages entering and leaving Arup business
systems are scanned for acceptability of content and viruses